1975-1996

During 1975 - 1988, the Company was reconstructed and modernized. Some plants were closed and the new ones were erected. In 1982, a new, second phosphoric acid production line, twice more powerful than the first one was built and launched while the old one was closed for the renovation. In 1984, a new, more powerful aluminium fluoride plant was built and the old one was closed. In 1985, the phosphoric acid plant No.1 came into operation after the reconstruction. In 1986, the third ammophos production line augmented the fertilizer production capacities. The renovation of the Company was finished in 1988, when new and modern sulphuric acid plant came into operation. The outworn plant was closed and dismantled.

In 1996, the company was privatized.